Requests for Proposals
Requests for Proposals
RFP #2027-01 AUDIO-VISUAL AND CONFERENCING SOLUTIONS
Region 9 Education Service Center is requesting proposals for audio-visual and conferencing solutions. The scope of work for complete replacement of all equipment to provide turnkey systems for audio-visual needs as follows:
- Core Rooms: Wichita Rooms, the Foard Room, and the Montague Room of the Region 9 ESC. Pricing needs to be listed per room, but this core will be awarded all or none.
- Possible Additional Rooms: Hardeman, Knox, Throckmorton, Clay (quoted individually). Region 9 ESC reserves the right to add any or all of these rooms to the core group. Awards for additional rooms will only be added to the awarded vendor of the core rooms group.
For a copy of the proposal specifications contact:
Dana Parrish, Administrative Specialist
Phone Number (940) 322-6928
Email Dana.Parrish@esc9.net
Sealed proposals, clearly marked “AV/Conferencing Solutions RFP #2027-01” on outside of sealed envelope, are due at Region 9 ESC, 301 Loop 11, Wichita Falls, TX, 76306, by 3:00 PM (CDT) on Wednesday, December 2, 2026. Proposals will be opened at Region 9 ESC at 3:15 PM the same day for preliminary review. Negotiations as necessary will take place December 3 - 15, and recommendation for award(s) will be presented to the ESC Board of Directors at their meeting currently scheduled for 12:30 PM, Wednesday, December 16, 2026 .
Failure to have a response submitted by the above deadline shall result in the response NOT being considered; fax or other electronic submissions shall NOT be considered. The selection of respondents shall be in accordance with Texas Education Code Chapter 44, if applicable, and Texas Government Code 2254.
REGION 9 ESC RESERVES THE RIGHT TO REJECT ANY OR ALL RESPONSES AND TO WAIVE IRREGULARITIES OR INFORMALITIES AS MAY BE DEEMED IN ITS BEST INTEREST.
WAIVER OF CLAIMS: BY TENDERING A RESPONSE TO THIS REQUEST FOR PROPOSALS, THE PROPOSER ACKNOWLEDGES THAT IT HAS READ AND FULLY UNDERSTANDS THE REQUIREMENTS FOR SUBMITTING A RESPONSE, AND THE PROCESS USED FOR SELECTING A PROVIDER. FURTHER, BY SUBMITTING A RESPONSE, THE PROPOSER FULLY, VOLUNTARILY AND UNDERSTANDINGLY WAIVES AND RELEASES ANY AND ALL CLAIMS AGAINST REGION 9 ESC, OR ANY OF ITS DIRECTORS, OFFICERS, AGENTS AND/OR EMPLOYEES THAT COULD ARISE OUT OF THE ADMINISTRATION, EVALUATION, OR RECOMMENDATION OF ANY RESPONSE SUBMITTED TO THIS REQUEST FOR PROPOSALS.
-------------------
11-13-2026 – An addendum to the original RFP was released to include a report for the 11-12-26 site visit (there were no participants for the 11-10-26 site visit), and to offer another site visit opportunity on 11-23-26 at 11:00 AM. Contact Dana Parrish at dana.parrish@esc9.net for a copy of the amended RFP, or to notify of plan to participate in 11-23-26 site visit.
11-25-26 – Addendum #2 to the RFP was released to include a report for the 11-23-26 site visit, and to clarify specifications. Contact Dana Parrish at dana.parrish@esc9.net for a copy of the amended RFP. (NOTE: Region 9 ESC is currently closed for the holidays and will re-open on Monday, November 30, 2026.)
QUESTIONS FROM PROSPECTIVE PROPOSERS
(Received by 12:00 PM on 11/24/26 - Posted as presented)
VENDOR A
Wichita 1 & 2
- Please clarify whether the two 216" DvLED displays and two 98" displays are contractor-provided or client-provided. The RFP identifies them as contractor-provided, while the walk-through documentation identifies them as client-provided.
Answer: The two 216’ DvLED displays and the 98’ displays will be contractor provided.
Hardeman
- The RFP document states that the new displays are "to work with the client provided TV's (already present). Please confirm whether the existing displays are to remain and be integrated into the new AV system or removed by the contractor.
Answer: Both TV’s will be new, and contractor provided. Old TV’s and equipment will be removed/taken down by the contractor. Region 9 ESC will discuss with awarded contractor whether removed equipment will be retained by Region 9 or is to be disposed by contractor during negotiation/pre-planning period.
Montague
- Please advise whether Storage Room 219A is an approved location for the new AV equipment rack.
Answer: 219A is not available for an equipment rack.
General Questions
- The RFP specifies two QSC touch panels per room, while the Wilbarger walkthrough example showed only one touch panel at the lectern. Please specify whether one or two touch panels are required per room. If two are required, please identify the intended mounting location of the second panel (wall, rack, or tabletop).
Answer: One touch panel per lectern is required.
- Please confirm that Wichita 1 & 2 are the only rooms requiring lectern input connections.
Answer: All rooms will need a lectern input connection. The inputs will be at the location of where each lectern is currently installed. Wichita 1 & 2 are the only locations where additional inputs are needed along with room customizations within the Q- SYS system, based on different room configurations.
VENDOR B QUESTIONS
1. Is the Podium the customer is providing have housing for the new equipment that will be installed?
Answer: The podium provided by the customer has the correct rack space housing for the equipment being installed. This was shown in the Willbarger rooms as an example of an already completed room.
2. Do we need to provide a rack for any of the 3 Main Rooms or the 4 Optional rooms?
Answer: Only if the current rack space is inadequate and more space is needed in an IDF.
3. Are we reusing the rack in the Wichita Room?
Answer: The Wichita Room rack is available for reuse if needed. If a bigger rack is required, please add the cost into your quote and spec sheet.
4. Are any of the existing displays in any of the rooms going to be reused? And if yes, is there an existing QSC decoder at the display?
Answer: No existing displays will be reused.
5. Will the customer be connecting a Laptop at the Podium for Video Conferencing in each room?
Answer: Yes, the podiums need to allow for HDMI, USB-C with power.
6. If any of the existing display are being reused, will any of them need to be relocated to a different wall in any of the rooms? Or will they stay in the same locations.
Answer: No existing displays will be kept for use in the proposed project. Region 9 ESC will discuss with contractor whether removed equipment will be retained by Region 9 or is to be disposed by contractor.
VENDOR C
- Which 216-inch Newline model should bidders use as the basis of comparison? What minimum pixel pitch, native resolution, brightness, and front-service access must an alternate meet? Are any built-in functions required, such as scheduled signage, playback without a room PC, or wireless casting?
Answer: Proposer should select model they feel will best fit the needs as specified in the RFP for best value and best presentation. Proposer may suggest multiple options for consideration during the negotiation process. The LED wall needs to be able to connect to the customer-provided PC which resides in the podium. No scheduled signage is required; all video feed will come from customer-provided computer; no wireless casting needed.
- Can Region 9 provide the available circuit capacity, outlet locations, wall construction or backing details, and cable pathways at both wall locations? Who will provide new circuits, outlet relocations, conduit, and any structural reinforcement?
Answer: Proposers had the opportunity to review walls, outlets, etc. during site visits. At this late date we cannot provide any further information. Region 9 will provide the electrician to meet the awarded proposer’s requirements. Structural reinforcement may be discussed during the negotiation process to determine whether appropriate tradespeople will be contracted by awarded proposer or Region 9 ESC.
- Should split/join room mode follow a partition sensor or be selected at the touch panels?
Answer: Both
- Can Region 9 provide the current Q-SYS equipment list and design files for Wichita and the recently renovated rooms? Which equipment and network services will be reused, and does compatibility mean shared AV routing between rooms or a consistent operator interface?
Answer: Proposers had the opportunity to review current equipment/take pictures during the site visit. See also Exhibit B. A/V Equipment in Wichita rooms is all to be new. All QSYS routing will talk back to the main QSYS system housed in the IDF in the Young Rooms. This was covered in the site visit walk through.
- Which conferencing platform will be used? Does Region 9 require a dedicated recording/streaming system, and if so, what must be captured in joined and divided modes, and where should recordings be saved?
Answer: Region 9 uses Zoom for conferencing. All software will run from customer-provided PC. Region 9 will not require any conferencing software subscriptions within this RFP proposal.
- What are the ADA requirements for these rooms? Assistive Listening? Captions? What is the capacity of the rooms?
Answer: Proposers are responsible for ensuring ADA compliance regarding height and placement of equipment. Proposer has no obligation to ensure software used by Region 9 meets ADA compliance (assistive listening/captions).
Room Capacities (for normal set-ups):
Clay – 24
Foard – 42
Hardeman – 20
Knox – 36
Montague – 48
Throckmorton – 20
Wichita – 220 combined, 110 each
VENDOR D
1. Display supply, retained equipment and required performance
Section 3.1, page 8 includes two 216-inch LED walls and two 98-inch confidence displays for Wichita 1 and 2, while Exhibit C, page 58 describes them as client-provided. Please confirm who supplies the displays, processors and mounts. In other rooms, which existing front displays remain, and does the new 98-inch display replace or supplement them (pages 8-11)? Are there mandatory display-resolution/performance criteria beyond the stated sizes, or reference models to match? Please identify the content that must remain legible, such as detailed documents, spreadsheets or training videos, and any known daylight/glare problems.
Answer: Please see answer (Vendor C, Question 1). There are no display resolution or performance criteria. Vendor will be selected based on cost and value. Content legibility is not a requirement for this RFP. All content will come from client’s provided PC.
2. Existing Q-SYS system, integration boundary and outages
Please provide the installed Core/controller, relevant AV/network equipment inventory, current Q-SYS design files, software version, licenses/capacity information and reference-room control-screen examples. Confirm access and permission to modify the existing design and identify any incumbent programming/vendor dependencies. Does compatibility require a consistent user experience only, or audio/video sharing with other rooms beyond Wichita 1 and 2? Must Archer, Wilbarger, Young and other existing rooms remain operational during programming, firmware changes and reboots? Please identify permitted shared-system outage windows and any temporary-service requirement. Sources: pages 7, 56 and 58-59.
Answer: Please see Answer (Vendor C, Question 4). The compatibility requirement was discussed during vendor site visit. Required functionality was shown through Wilbarger room as an example. Firmware and upgrades must be scheduled with Region 9 to ensure day to day interruption is impacted. Shared system outage windows and temporary service requirement will not be given at this time, but can be discussed during negotiation talks if vendor is chosen.
3. Wireless microphone quantities and facility use
Page 8 specifies two handheld and one lavalier microphone per Wichita room; Exhibit C, page 58 calls for four wireless microphones per room. Please confirm simultaneous channels and transmitter types per room and in combined operation, and any Region 9-supplied wireless equipment. Please provide available model/frequency records for retained wireless systems and identify adjacent rooms that may operate simultaneously. Will microphones remain assigned to rooms or move between them?
Answer: Wichita 1 will need the functionality of two handheld microphones and two lavalier microphones in use simultaneously. Wichita 2 will need the functionality of two handheld microphones and two lavalier microphones in use simultaneously. When Wichita 1 and 2 are combined, Wichita 1 & 2 together should be able to run 8 microphones together simultaneously.
4. Lectern HDMI, USB-C and charging
May HDMI, USB-C laptop connectivity and charging be provided through an adjacent lectern-mounted interface alongside the touch panel? Exhibit B, page 55 lists the touch-panel USB-C connection for future use and lists no HDMI input, while page 61 requests these connections and charging from the panel. Please confirm minimum USB-C charging power and whether a guest laptop must have access to the room cameras and microphones as well as presentation video.
Answer: Please see answer to Vendor B, Question 5.
5. Presentation, conferencing, recording and Wichita operating modes
Please confirm whether the room AV equipment must support both the provided room computer and guest-laptop hosting, and whether Wichita must support simultaneous independent meetings when divided. For each room/mode, should front and confidence displays mirror content or show different material, such as presentation, presenter notes and remote participants? Which inputs/lecterns must be usable, and how are the displays, microphones, speakers and five Wichita cameras shared when combined? Should partition mode follow a sensor or manual selection, and which control-screen functions/permissions must match the reference rooms? Describe the required automatic camera behavior. Is recording through the supplied PC/meeting platform sufficient, or is separate recording/streaming required? If separate, identify required feeds, destination and applicable recording/storage/privacy restrictions. Sources: pages 8-11, 56 and 58-59.
Answer: Yes, AV equipment must support both the provided room computer and guest-laptop hosting. Yes, Wichita must support simultaneous independent meetings when divided. Each Wichita room/mode, should offer mirrored content or show different material, such as presentation, presenter notes and remote participants as determined by presenter. Each podium will require an input that allows for connectivity to all screens in the Wichita 1 and 2 rooms when combined, but also the flexibility for different configuration arrangements to be discussed during negotiation and pre-planning meetings. Camera placement will be discussed at negotiation and pre-planning meetings. Recording will be through the supplied PC.
6. Hardeman input quantities and touch-panel locations
Hardeman's page 9 podium-cabling paragraph refers to Wilbarger 1 and 2 and two 24-foot cables, while Exhibit C, pages 57-58 identifies one input location. Please confirm Hardeman's input locations and podium cable quantity. For single rooms specifying two touch panels, please identify intended locations.
Answer: Hardeman will only require one input location with one touch panel at the podium, location was discussed during walk-through. Requires one 24 foot cable (see Addendum 2).
7. Room photographs, measurements, cable routes and work access
Please provide available dimensioned/as-built drawings, photographs or a recorded walkthrough for every core and optional room. The following records or site access are needed:
- Room dimensions, seating/presenter layouts, nearest/farthest viewing positions, ceiling height, height to supporting structure, acoustic treatments and known noise/echo problems.
- Removable tile, hard ceiling, exposed structure or mixed conditions along rooms and routes; access openings, above-ceiling space and obstructions.
- Rack-to-device cable routes, approximate distances and vertical drops, existing conduit/tray/raceway, spare capacity, penetrations and barriers. Include available facilities/HVAC/life-safety records identifying return-air spaces or fire-rated assemblies for confirmation by the responsible trades.
- Existing cable schedules, labels, type/rating and test records, reuse authorization, and circuits/devices that must stay operational during cutover. The 24-foot lectern leads do not establish permanent rack-to-room run lengths.
- Display-wall construction and documented backing/support; structural information for suspended microphones and Montague's confidence display. Photographs alone cannot confirm concealed backing or capacity.
- Room-labeled rack photographs front/rear, equipment labels, available rack space/depth, ventilation, receptacles/circuit records and network connections; identify the rack serving each room.
- Lectern positions/movement, floor boxes/wall plates, and restrictions on floor raceway or exposed cable coverings.
- Permitted work hours, room downtime, security/access, lift/loading access, staging/storage and restrictions on noisy or dusty work. The one-room-at-a-time requirement is understood.
Useful photos include all room corners, display walls, ceilings, lectern/input areas, racks and accessible route/above-ceiling conditions where safe and permitted. Include Wichita's partition/high ceilings and Montague's confidence-display position. If records are unavailable, can a measurement visit or staff-assisted video walkthrough be arranged? Exhibit A, page 53 is a basic floor plan; pages 11 and 59-60 identify mounting responsibilities and special conditions.
Answer: Photos will not be provided by Region 9 ESC. Proposers had opportunity to attend site visits to take photos as they determined necessary.
8. Funding and project-specific compliance
Please identify funding source(s) and confirm applicable project-specific domestic sourcing and prevailing-wage requirements under the EDGAR forms. If applicable, provide the controlling wage determination and required product-origin documentation (pages 40-48).
Answer: Funding may be provided by local, state, or federal funds. Region 9 ESC’s policies and procedures require all purchasing and contracts meet the strictest standard and therefore require proposers to respond to the EDGAR supporting forms.
9. Procurement, payment and committed equipment
Page 13 states that no prepayments will be made and directs vendors to disclose deposit or periodic-payment needs. May the proposal include equipment procurement and room-completion payment milestones? Confirm treatment of committed, noncancelable equipment and restocking charges if Region 9 terminates after orders are placed (Part 6, section 42.1, pages 26-27). If applicable to an out-of-state proposer, please clarify the sales-tax presentation required by section 3.5 in light of Region 9's stated Texas sales-tax exemption.
Answer: Deposits and/or pre-payment milestones can be requested and will become part of the negotiation process. Region 9 ESC is exempt from Texas sales tax and will provide the awarded vendor with appropriate documentation.
10. Audio use, speaker matching and existing systems
Which microphones must be heard through room speakers as well as by remote participants? Are ceiling microphones for conferencing pickup only, or is local voice reinforcement also required? Does speaker matching mean the same manufacturer/model as the spring-2026 rooms, or a consistent proposed system across awarded rooms with comparable operation/performance? Please identify reference speaker models and mandatory appearance requirements. If Wahsega clock/speaker devices must move, who authorizes/performs that work and preserves their existing service? New AV-to-paging integration is not being assumed. Sources: pages 8-11, 56 and 61.
Answer: All audio within the scope of this project will come out of the house speakers installed by the proposer. Audio from Wahsega signs is not within the scope of this project.
11. Network access and remote support
Will Region 9 permit an IT-approved remote connection to the AV equipment through an AV VLAN with VPN access, or another connection method approved by IT? Please identify who approves and provisions that connection, any access/maintenance windows, and which network switches, ports and configuration Region 9 will provide versus the vendor.
With approved remote access, 210 Solutions will provide immediate telephone support and escalation, with onsite attendance within 24 hours when required. If remote access is unavailable, equipment troubleshooting and service will require onsite attendance.
Answer: Yes, Region 9 ESC will allow remote support and will configure an isolated VLAN for VPN access. Access/maintenance windows, switches, ports and configuration will be part of the discussion of the negotiation process as needed and the resulting pre-planning meetings with awarded vendor.
12. Acceptance, training and support commencement
Please identify acceptance authority and any required acceptance demonstrations beyond the vendor's commissioning plan. Does the one-year support period start with each room's acceptance or overall project completion? We will include training, operating/troubleshooting guides, a training video and system documentation; please identify any mandatory training quantities, audiences or handover formats beyond the RFP (pages 7, 12-13).
Answer: The one-year support period should start with the completion of the overall project. Walk-through and training of technology staff (approximately 2 people) should be provided after the completion of each room. Additional details of the training process will be part of the negotiation process.